Mandaue City speeds up flood control projects ahead of monsoon season

Mandaue City speeds up flood control projects ahead of monsoon season
Mandaue City Hall.File photo
Published on: 
Summary
  • Mayor Thadeo Jovito “Jonkie” Ouano ordered Mandaue City to rush drainage upgrades and river cleanups to protect flood-prone communities ahead of the upcoming southwest monsoon season.

  • Excavation delays caused by underground utility lines extended the completion date of a critical bypass drainage project in Barangay Tipolo from May to late June.

  • The City is launching a year-long, zero-cost Butuanon River dredging project to remove heavy siltation that causes the waterway to overflow into surrounding communities during heavy rains.

MANDAUE City is rushing to complete major drainage improvements and river cleanup projects to protect residents from the upcoming southwest monsoon season. Under direct orders from Mayor Thadeo Jovito “Jonkie” Ouano, local offices and contractors are focusing their efforts entirely on the city's most flood-prone communities. This urgent push comes as the City braces for heavy seasonal rains that frequently overwhelm local infrastructure and disrupt daily life.

Changing how the City handles floodwaters

The core challenge facing Mandaue is managing the massive volume of water that arrives during severe weather. While older infrastructure often left certain areas submerged in waist-deep or chest-deep water, the City's current upgrades aim to rapidly accelerate water runoff.

City officials note that while climate change and mountain runoff make it impossible to eliminate flooding entirely, the new infrastructure targets reducing water levels to ankle-deep levels that recede quickly.

Fixing bottlenecks in local drainage

A primary driver of localized flooding is structural bottlenecks that trap stormwater in low-lying areas. To resolve this, the City is constructing a bypass drainage system in Barangay Tipolo to connect drainage lines from the national highway directly to Tipolo Creek. The new line cuts through a private warehouse property to create a direct outlet for the water.

Originally scheduled for completion in May, the project received a one-month extension to late June due to excavation delays caused by underground electrical and telecommunications lines.

Similar drainage openings completed near the Cebu Rolling Hills Memorial Chapel on A.S. Fortuna St. have already demonstrated the effectiveness of this approach. City Administrator Gonzalo “Sally” Malig-on noted that complaints about flooding in that area have significantly decreased since completion.

“We cannot stop the rain and we cannot stop the water coming from the mountains. What we can do is make sure the water leaves quickly,” Malig-on said.

Restoring river capacity through dredging

Beyond neighborhood drainage networks, the City is addressing the broader environmental causes of overflow along its major waterways. Heavy silt accumulation has drastically reduced the capacity of local rivers, causing them to spill over into surrounding communities during intense rainfall.

To combat this, the City is launching a large-scale dredging operation along a 3.4 to 3.6-kilometer stretch of the Butuanon River, from its mouth at Channel 2 to the bridge near Pacific Mall.

“The river has become heavily silted. When the water level rises during strong rains, the capacity of the river is reduced, causing it to overflow into surrounding communities,” Malig-on explained.

The year-long dredging project is structured as a corporate social responsibility initiative, partnered with the Department of Public Works and Highways, meaning it will require no funding from the City Government. Heavy equipment from Manila is scheduled to mobilize in June as operational details are finalized.

To prevent ongoing utility delays from slowing these critical projects, the City has instituted regular coordination meetings between engineers, utility providers, barangay officials and traffic management personnel to ensure deadlines are met. / ABC