Lubuagan eyed for hydro project

Johanna O. Bajenting, Mae Fhel Gom-os

SAN Lorenzo Ruiz Builders and Developers Group Inc. is eyeing the municipality of Lubuagan in Kalinga for the setup of a hydroelectric dam project in the town.

Jonas Azuelo, spokesperson of the company, said the project hopes to generate 150 megawatts.

Azuelo said the service contract for the Lubuagan area was issued by the Department of Energy as early as 2014 and the company is revisiting possibilities now after failed attempts to set up years ago.

Lubuagan Mayor Johnny Dickpus is welcoming the company in the town anew after talks collapsed in the past because of opposition from locals.

The area of the project has since been relocated from the Lucog area to a new site yet to be disclosed.

San Lorenzo Ruiz Builders and Developers Group Inc. is exploring possibilities in other areas in the province after elders submitted a petition of protest to the 52-megawatt hydroelectric dam project along the Chico River.

The project is spearheaded by Oscar Violago of Nueva Ecija under the San Lorenzo Builders and Developers Group (Karayan Incorporated).

Opposition includes members of the Naneng, Dallak and Minanga sub-tribes and the residents of sitio Banat, Bagumbayan who have land directly to be affected by the project.

National Commission on Indigenous Peoples Regional Director Ronald Calde has ruled to resolve all impasses before proceeding with the Kalinga Chico river project.

Calde said if and when these conflicts are resolved, it is only when the project will continue its Free, Prior and Informed Consent process.

Anti-flood Task Force targets gov’t offices

City sports center revamp 50% done as Palaro looms

DOH: Delayed Covid allowances ‘underway’

Cedric Lee, Deniece Cornejo ‘guilty’ in Vhong Navarro illegal detention for ransom case

HIV ‘not a legal ground’ to terminate employees